Name: Auto 2025-10-11
Routing metric: Travel time
No Restrictions Applied.
Station Name: TS 1
Address: Filonos 2-8, Keratsini 187 57
Path ID: 142548
Truck: Truck auto 345 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.89 m³
Duration: 00:13:56
Travel Duration: 00:08:56
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:56:32
Slack: 23:03:27
Path ID: 142549
Truck: Truck auto 367 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.95 m³
Duration: 00:13:18
Travel Duration: 00:07:18
Wait Duration: 00:00:00
Service Duration: 00:06:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:54
Slack: 23:04:05
Path ID: 142550
Truck: Truck auto 455 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.54 m³
Duration: 00:11:02
Travel Duration: 00:06:02
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:38
Slack: 23:06:21
Path ID: 142551
Truck: Truck auto 481 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.89 m³
Duration: 00:11:20
Travel Duration: 00:06:20
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:56
Slack: 23:06:03
Path ID: 142552
Truck: Truck auto 491 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.9 m³
Duration: 00:11:32
Travel Duration: 00:07:32
Wait Duration: 00:00:00
Service Duration: 00:04:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:08
Slack: 23:05:51
Path ID: 142553
Truck: Truck auto 523 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 16.0 m³
Duration: 00:12:20
Travel Duration: 00:07:20
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:56
Slack: 23:05:03
Path ID: 142554
Truck: Truck auto 605 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.76 m³
Duration: 00:12:56
Travel Duration: 00:07:56
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:32
Slack: 23:04:27
Path ID: 142555
Truck: Truck auto 621 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.58 m³
Duration: 00:12:56
Travel Duration: 00:07:56
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:32
Slack: 23:04:27
Path ID: 142556
Truck: Truck auto 655 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 14.51 m³
Duration: 00:10:30
Travel Duration: 00:06:30
Wait Duration: 00:00:00
Service Duration: 00:04:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:06
Slack: 23:06:53
Path ID: 142557
Truck: Truck auto 687 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.54 m³
Duration: 00:12:27
Travel Duration: 00:07:27
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:03
Slack: 23:04:56
Path ID: 142558
Truck: Truck auto 707 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.81 m³
Duration: 00:11:00
Travel Duration: 00:06:00
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:36
Slack: 23:06:23
Path ID: 142559
Truck: Truck auto 731 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.99 m³
Duration: 00:14:02
Travel Duration: 00:09:02
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:56:38
Slack: 23:03:21
Path ID: 142560
Truck: Truck auto 751 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.53 m³
Duration: 00:10:39
Travel Duration: 00:05:39
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:15
Slack: 23:06:44
Path ID: 142561
Truck: Truck auto 855 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.96 m³
Duration: 00:11:12
Travel Duration: 00:06:12
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:48
Slack: 23:06:11
Path ID: 142562
Truck: Truck auto 859 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.53 m³
Duration: 00:13:12
Travel Duration: 00:08:12
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:48
Slack: 23:04:11
Path ID: 142563
Truck: Truck auto 901 - 16.0m³ - GENERAL
Date: 2025-10-11
Personnel:
Load: 15.72 m³
Duration: 00:12:32
Travel Duration: 00:08:32
Wait Duration: 00:00:00
Service Duration: 00:04:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:55:08
Slack: 23:04:51
Path ID: 142564
Truck: Truck auto 8 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.9 m³
Duration: 00:11:33
Travel Duration: 00:06:33
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:09
Slack: 23:05:50
Path ID: 142565
Truck: Truck auto 10 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.9 m³
Duration: 00:12:04
Travel Duration: 00:07:04
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:40
Slack: 23:05:19
Path ID: 142566
Truck: Truck auto 34 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.68 m³
Duration: 00:11:05
Travel Duration: 00:06:05
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:41
Slack: 23:06:18
Path ID: 142567
Truck: Truck auto 38 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.63 m³
Duration: 00:12:18
Travel Duration: 00:07:18
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:54
Slack: 23:05:05
Path ID: 142568
Truck: Truck auto 42 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.77 m³
Duration: 00:12:19
Travel Duration: 00:07:19
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:55
Slack: 23:05:04
Path ID: 142569
Truck: Truck auto 92 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.9 m³
Duration: 00:12:09
Travel Duration: 00:07:09
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:45
Slack: 23:05:14
Path ID: 142570
Truck: Truck auto 102 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.9 m³
Duration: 00:10:43
Travel Duration: 00:05:43
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:19
Slack: 23:06:40
Path ID: 142571
Truck: Truck auto 196 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.82 m³
Duration: 00:12:13
Travel Duration: 00:07:13
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:54:49
Slack: 23:05:10
Path ID: 142572
Truck: Truck auto 208 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-11
Personnel:
Load: 15.22 m³
Duration: 00:11:16
Travel Duration: 00:06:16
Wait Duration: 00:00:00
Service Duration: 00:05:00
Release Time: 00:00:00
Start Time: 00:42:36
End Time: 00:53:52
Slack: 23:06:07