Name: Auto 2025-10-19
Routing metric: Travel time
No Restrictions Applied.
Station Name: TS 1
Address: Filonos 2-8, Keratsini 187 57
Path ID: 147020
Truck: Truck auto 792 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-10-19
Personnel:
Load: 9.6 m³
Duration: 00:10:05
Travel Duration: 00:04:05
Wait Duration: 00:00:00
Service Duration: 00:06:00
Release Time: 00:00:00
Start Time: 00:30:04
End Time: 00:40:09
Slack: 23:19:50
(Truck Station) TS 1 Filonos 2-8, Keratsini 187 57
Start service: 00:30:04
End service: 00:30:04
Service duration: 00:00:00
Wait duration: 00:00:00
Completed: false
Waste Type: GENERAL_RECYCLING
Load: 1.1615812008401012 m³
Capacity: 2.0 m³
Start service: 00:31:52
End service: 00:32:52
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.9907703236171106 m³
Capacity: 2.0 m³
Start service: 00:32:58
End service: 00:33:58
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.7691416614300892 m³
Capacity: 2.0 m³
Start service: 00:34:12
End service: 00:35:12
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.6467678390715035 m³
Capacity: 2.0 m³
Start service: 00:35:16
End service: 00:36:16
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.3897782049152405 m³
Capacity: 2.0 m³
Start service: 00:36:42
End service: 00:37:42
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.6777584661504243 m³
Capacity: 2.0 m³
Start service: 00:37:46
End service: 00:38:46
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
(Truck Station) TS 1 Filonos 2-8, Keratsini 187 57
Start service: 00:40:09
End service: 00:40:09
Service duration: 00:00:00
Wait duration: 00:00:00
Completed: false