Name: Auto 2025-11-27
Routing metric: Travel time
No Restrictions Applied.
Station Name: TS 1
Address: Filonos 2-8, Keratsini 187 57
Path ID: 190145
Truck: Truck auto 337 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.62 m³
Duration: 00:18:59
Travel Duration: 00:07:59
Wait Duration: 00:00:00
Service Duration: 00:11:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:49:02
Slack: 22:10:57
Path ID: 190146
Truck: Truck auto 425 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.51 m³
Duration: 00:16:37
Travel Duration: 00:07:37
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:40
Slack: 22:13:19
Path ID: 190147
Truck: Truck auto 531 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 14.33 m³
Duration: 00:14:30
Travel Duration: 00:05:30
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:44:33
Slack: 22:15:26
Path ID: 190148
Truck: Truck auto 571 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.55 m³
Duration: 00:16:26
Travel Duration: 00:06:26
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:29
Slack: 22:13:30
Path ID: 190149
Truck: Truck auto 607 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 14.5 m³
Duration: 00:17:12
Travel Duration: 00:07:12
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:15
Slack: 22:12:44
Path ID: 190150
Truck: Truck auto 639 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.16 m³
Duration: 00:18:57
Travel Duration: 00:07:57
Wait Duration: 00:00:00
Service Duration: 00:11:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:49:00
Slack: 22:10:59
Path ID: 190151
Truck: Truck auto 681 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.86 m³
Duration: 00:16:45
Travel Duration: 00:07:45
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:48
Slack: 22:13:11
Path ID: 190152
Truck: Truck auto 707 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 13.96 m³
Duration: 00:14:12
Travel Duration: 00:06:12
Wait Duration: 00:00:00
Service Duration: 00:08:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:44:15
Slack: 22:15:44
Path ID: 190153
Truck: Truck auto 809 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.78 m³
Duration: 00:17:05
Travel Duration: 00:07:05
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:08
Slack: 22:12:51
Path ID: 190154
Truck: Truck auto 873 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.83 m³
Duration: 00:16:06
Travel Duration: 00:07:06
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:09
Slack: 22:13:50
Path ID: 190155
Truck: Truck auto 925 - 16.0m³ - GENERAL
Date: 2025-11-27
Personnel:
Load: 15.71 m³
Duration: 00:18:11
Travel Duration: 00:08:11
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:48:14
Slack: 22:11:45
Path ID: 190156
Truck: Truck auto 54 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.94 m³
Duration: 00:18:22
Travel Duration: 00:08:22
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:48:25
Slack: 22:11:34
Path ID: 190157
Truck: Truck auto 58 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.99 m³
Duration: 00:19:58
Travel Duration: 00:08:58
Wait Duration: 00:00:00
Service Duration: 00:11:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:50:01
Slack: 22:09:58
Path ID: 190158
Truck: Truck auto 100 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.98 m³
Duration: 00:18:13
Travel Duration: 00:08:13
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:48:16
Slack: 22:11:43
Path ID: 190159
Truck: Truck auto 104 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.78 m³
Duration: 00:16:15
Travel Duration: 00:07:15
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:18
Slack: 22:13:41
Path ID: 190160
Truck: Truck auto 150 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.94 m³
Duration: 00:17:40
Travel Duration: 00:08:40
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:43
Slack: 22:12:16
Path ID: 190161
Truck: Truck auto 178 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.96 m³
Duration: 00:15:24
Travel Duration: 00:06:24
Wait Duration: 00:00:00
Service Duration: 00:09:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:45:27
Slack: 22:14:32
Path ID: 190162
Truck: Truck auto 266 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.78 m³
Duration: 00:17:12
Travel Duration: 00:07:12
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:15
Slack: 22:12:44
Path ID: 190163
Truck: Truck auto 270 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.56 m³
Duration: 00:17:14
Travel Duration: 00:07:14
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:17
Slack: 22:12:42
Path ID: 190164
Truck: Truck auto 340 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.75 m³
Duration: 00:17:11
Travel Duration: 00:07:11
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:14
Slack: 22:12:45
Path ID: 190165
Truck: Truck auto 356 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 16.0 m³
Duration: 00:16:36
Travel Duration: 00:06:36
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:39
Slack: 22:13:20
Path ID: 190166
Truck: Truck auto 412 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.87 m³
Duration: 00:16:20
Travel Duration: 00:06:20
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:46:23
Slack: 22:13:36
Path ID: 190167
Truck: Truck auto 418 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.87 m³
Duration: 00:18:24
Travel Duration: 00:07:24
Wait Duration: 00:00:00
Service Duration: 00:11:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:48:27
Slack: 22:11:32
Path ID: 190168
Truck: Truck auto 424 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.98 m³
Duration: 00:19:46
Travel Duration: 00:07:46
Wait Duration: 00:00:00
Service Duration: 00:12:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:49:49
Slack: 22:10:10
Path ID: 190169
Truck: Truck auto 502 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-11-27
Personnel:
Load: 15.59 m³
Duration: 00:17:17
Travel Duration: 00:07:17
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 01:30:03
End Time: 01:47:20
Slack: 22:12:39