Name: Auto 2025-07-03
Routing metric: Travel time
No Restrictions Applied.
Station Name: TS 1
Address: Filonos 2-8, Keratsini 187 57
Path ID: 85679
Truck: Truck auto 22 - 16.0m³ - GENERAL_RECYCLING
Date: 2025-07-03
Personnel:
Load: 15.97 m³
Duration: 00:13:45
Travel Duration: 00:03:45
Wait Duration: 00:00:00
Service Duration: 00:10:00
Release Time: 00:00:00
Start Time: 00:30:04
End Time: 00:43:49
Slack: 23:16:11
(Truck Station) TS 1 Filonos 2-8, Keratsini 187 57
Start service: 00:30:04
End service: 00:30:04
Service duration: 00:00:00
Wait duration: 00:00:00
Completed: false
Waste Type: GENERAL_RECYCLING
Load: 1.4 m³
Capacity: 2.0 m³
Start service: 00:31:03
End service: 00:32:03
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 0.24 m³
Capacity: 2.0 m³
Start service: 00:32:12
End service: 00:33:12
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 0.01 m³
Capacity: 2.0 m³
Start service: 00:33:21
End service: 00:34:21
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.79 m³
Capacity: 2.0 m³
Start service: 00:34:46
End service: 00:35:46
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.2 m³
Capacity: 2.0 m³
Start service: 00:35:54
End service: 00:36:54
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.04 m³
Capacity: 2.0 m³
Start service: 00:37:07
End service: 00:38:07
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 0.12 m³
Capacity: 2.0 m³
Start service: 00:38:14
End service: 00:39:14
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.88 m³
Capacity: 2.0 m³
Start service: 00:39:22
End service: 00:40:22
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.32 m³
Capacity: 2.0 m³
Start service: 00:40:33
End service: 00:41:33
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
Waste Type: GENERAL_RECYCLING
Load: 1.02 m³
Capacity: 2.0 m³
Start service: 00:41:41
End service: 00:42:41
Service duration: 00:01:00
Wait duration: 00:00:00
Completed: true
(Truck Station) TS 1 Filonos 2-8, Keratsini 187 57
Start service: 00:43:49
End service: 00:43:49
Service duration: 00:00:00
Wait duration: 00:00:00
Completed: false